Prior to installing any UST system, the owner/operator must obtain the required permit from the _________.

Explanation:
Installing underground storage tanks is treated as a construction activity. Before work begins, a permit is needed to review plans and ensure the site complies with local building codes, zoning, safety requirements, and proper construction details like containment and corrosion protection. The local building official is the authority responsible for issuing this permit because they oversee building permits and code compliance in the area, coordinating with other agencies as needed. While fire safety or environmental requirements may also come into play and additional approvals might be required, the formal permit to start installation typically comes from the local building department.

Installing underground storage tanks is treated as a construction activity. Before work begins, a permit is needed to review plans and ensure the site complies with local building codes, zoning, safety requirements, and proper construction details like containment and corrosion protection. The local building official is the authority responsible for issuing this permit because they oversee building permits and code compliance in the area, coordinating with other agencies as needed. While fire safety or environmental requirements may also come into play and additional approvals might be required, the formal permit to start installation typically comes from the local building department.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy